West Virginia Blue
The Best Blogging Community in West Virginia
Democratic politics, progressive policies, the good life and free living in Wild, Wonderful West Virginia.
Big Daddy Sen. Robert C. Byrd

A lawyer's take on the Maryland PSC's PATH hearing

by: blonde moment

Mon Aug 03, 2009 at 17:31:30 PM EDT


Posted by blonde moment

Doug Kaplan, president of the Sugarloaf Conservancy in Maryland, gave me permission to post the summary prepared by the group's attorney about the hearing last Friday before the Maryland Public Service Commission.

Members of the Sugarloaf Conservancy, Inc., as well as interested citizens and property owners from Urbana and Mt. Airy, principally, attended the hearing before the Public Service Commission ("PSC") today on the application of Potomac Edison on behalf of PATH (a conglomerate of various transmission companies and groups, including Allegheny Power and AEP) which seeks to build transmission lines and a substation near Mt. Airy.

The hearing commenced at 10:00 AM with four of the five commissioners present. The hearing was focused on four questions which the PSC had requested the parties to brief, dealing with procedural and jurisdictional issues to determine if they would accept the application for filing. Presentations were made by the attorneys for the several parties, including the Applicant, Frederick County, the Sierra Club, Office of Peoples Counsel, Staff of the Public Service Commission and Jim Thompson, attorney for the Sugarloaf Conservancy, Inc. In addition, individual presentations were made by eight to ten citizen / intervenors addressing a variety of issues including the lack of notice the Applicant had given to citizens.

As a result of the hearing, it appears that the PSC will issue a decision within the next two weeks with several of these findings:

blonde moment :: A lawyer's take on the Maryland PSC's PATH hearing
A. That the PSC does not have jurisdiction to consider the application of Potomac Edison on behalf of PATH since PATH is not an electric company, and PSC is restricted by statute in this regard. It appears likely that they will permit the applicant to amend their application and make Potomac Edison the applicant since it is an electric company under the statute; however, PATH has the financing and the rate approval from the Federal Energy Regulatory Commission ("FERC") and does not wish to do that.

B. That Potomac Edison cannot assign a CPCN ("Certificate of Public Convenience and Necessity") to a non-electric company to satisfy the statute. There are no rules or principles to cover this.

C. That the Frederick County Planning Board and County Commissioners have jurisdiction to hear the special exception necessary for the siting of the substation. Frederick County maintains that it has jurisdiction to hear the land use issues and decide on the siting of the substation. However, the Public Service Commission has authority to determine the location of the transmission lines and possibly, as the applicant maintains, the substation can be considered an integral part of the transmission lines. Hence, there can be several different outcomes with either Frederick or the PSC with exclusive jurisdiction or some type of a shared decision making process.

D. That FERC has "back stop" authority if the PSC does not make a decision on the merits of the application within twelve months after a proper application has been filed with the PSC. Concerns were expressed about when the one-year time clock begins to run and how much time the PSC has left to address the issues on the merits, since the application in this case was filed on May 19, 2009. Since the applicant did not file as an electric company, a powerful argument can be made that the time clock for the FERC back stop authority has not yet begun to run. Discussion was had about whether PSC would permit the applicant to amend its application with the understanding that the one-year time clock would begin to run from that date, but the PSC's view on this is unclear.

The hearing before the PSC lasted until 2:00 PM. We expect the Public Service Commission to issue an order within the next two weeks and we will see how it addresses these several questions, and whether our instincts are correct in this initial evaluation.

Tags: , , , , , , (All Tags)
Print Friendly View Send As Email

thank you for posting this (0.00 / 0)
It is very helpful to know what's going on in other states impacted by the same issues.

The situation in WV is at once worse and better than in MD. (0.00 / 0)
WV statute allows any kind of company to apply for a certificate of need, but a certificate of need can only be issued to a public utility.  This creates an absurd situation which actually happened in the TrAIL case last year.  

TrAILCo, Allegheny Energy's front company, was not a public utility when it applied for a certificate of need, so, in its order granting the certificate of need, the WV PSC had to declare that TrAILCo was a public utility, although TrAILCo had only existed for a few months and had contracted all operation of the TrAIL line to Allegheny Energy.

Under WV law, a public utility must provide a public service.  Although this is a very vague definition, acting as a landlord for a power line is clearly not providing a public service.

The four (count 'em, four) front companies applying for the PATH certificate of need have also asked for the WV PSC to hit them on the head with a magic wand and turn them into public utilities.  This is ridiculous.  It is quite likely that a number of intervenors will object to this charade in the coming months.  I already have.

WV is not under threat of federal takeover, because the US Fourth Circuit declared this FERC rule is unconstitutional in the Fourth Circuit.  MD remains under this federal threat because MD is not in the Fourth Circuit.


Thanks for the 4th Circuit info (0.00 / 0)
That's an aspect I hadn't thought of. Does the Fourth Circuit provide precedent, or a guide, to what might happen in other circuits?

[ Parent ]
No. (0.00 / 0)
Their ruling only has force in their own circuit.

[ Parent ]
Yes. Md is Fourth Circuit also. (0.00 / 0)
brother-in-law works at SCOTUS, administrative office, his email is ao.uscourts.gov so look at this. Maryland. West Virginia are both Fourth Circuit. Penn. and New Jersey are Third, that's the opportunity for a different ruling and another shot at SCOTUS, unless Sen. Bingaman has '"fixed" it first.

NFTT: Support My Team or I Will Dance

[ Parent ]
need a recap (0.00 / 0)
Sorry for being slow on this one, I'm getting lost in the 4th circuit weeds here... please lay it out for me really simple, I get the feeling this could be important. :-)

The court ruled what? The ruling means what to the PATH case?


Thanks to CA Berkeley (0.00 / 0)
for the correction on the Fourth Circuit. Clem, remember Cheney's secret energy task force at the beginning of his administration?  That task force came up with an agenda that would federalize the process of building huge new transmission lines that would enable Cheney's buddies like Kenny Boy Lay to trade electricity till the cows came home.  Kenny Boy screwed it all up in California and Enron collapsed, but Citigroup and Goldman Sachs have filled Enron's shoes.

A key part of the Cheney agenda was written into law by the 2005 National Energy Policy Act, passed by the Republican controlled Congress.  That law established the National Impact Energy Transmission Corridors around the US where FERC decided there was electrical system "congestion."  This congestion is not what you and I think of as congestion, but that discussion is for another time.  Suffice it to say that this congestion is about whether traders can make money, "economic congestion," and is not about lines melting or the grid collapsing.  That discussion is for another time.

44 of WV's 55 counties were designated as falling within NIETC in the eastern part of the US, basically all but the most southern counties.  The NIETC designation was designed to allow the Federal Energy Regulatory Commission to step in and impose federal eminent domain power to seize land for power lines if state regulatory agencies, much closer to pressure from citizens and land owners (remember them?), either refused or failed to act on an application for approval.

The law said that a state PSC must act on a proposed line within one year to rule on a line or FERC could step in.  FERC interpreted the law to also mean that if a state PSC considered a certificate of need and turned it down, FERC could step in and force the construction of the line.

In Loudoun County, Virginia there is a wonderful organization called the Piedmont Environmental Council.  They are involved in a wide range of issues including the preservation of farmland and the promotion of farmers markets, but they also were major players in the TrAIL line case in VA.  They are also one of the leading groups in the VA section of the PATH line, which also goes through Loudoun County.

In 2008, the PEC took FERC to the US Fourth Circuit over its interpretation of the 2005 NIETC law.  In February 2009, the Fourth Circuit ruled that NIETC applies if a state agency fails to take any action in a power line case, but that if a state PSC affirmatively rules against a power line, there is nothing FERC can do to overturn that decision.

This decision was a major victory.  While I think this argument is wrong, because I think state politicians and PSCs should stand up for their citizens against federal tyranny, there was an argument that if FERC could take over a project anyway, a state PSC should approve a power line, just so they could remain in the process.  If they denied a power line and FERC stepped in, then the state would be completely out of the picture.  In fact, in 2006, you can find this letter on The Power Line, Gov. Manchin wrote a letter to the Secretary of the Dept. of Energy, encouraging FERC to take over the TrAIL and PATH projects to force them through.  Read this letter.  It puts all Manchin's more recent claims about how he is "neutral" on the power lines into a much clearer perspective.

In any case, for the time being, in the Fourth Circuit, if a state PSC turns down PATH, that's it.  FERC cannot force the issue.  AEP CEO Mike Morris wants the Fourth Circuit opinion overturned by the new energy bill in the Congress now.  Morris said last Friday that he is confident that Sen. Bingaman's Senate bill will "fix," in his words, the House Waxman Markey bill that has extended the Fourth Circuit to the whole eastern US.

The apparent problem in the MD case is that no one really knows what the 2005 law meant when it said that FERC could step in after one year if a PSC failed to act.  Does "to act" mean just accepting an application for consideration or does it mean actually rendering a decision?  No one really knows.  So the MD PSC is apparently worried that if they force the power companies to reapply in MD, FERC would claim that their clock started ticking in May 2009.  If the process had to start all over again, it is unlikely that MD's PSC could render a decision by May 2010.  So they are afraid that FERC would consider that the PSC was stalling and assert their control at that point.

I personally think this is not a big concern.  WV statute requires that the WV PSC render a decision in 400 days, well more than a year.  The WV PSC even extended this deadline in the TrAIL case, and FERC didn't make a peep.  I think the concerns in MD are just being stirred up by the power companies to pressure the PSC.

Sorry for the long explanation, but this stuff is very complicated.  But it can be understood, and it is important that we understand it.


[ Parent ]
thanks, that is really helpful (0.00 / 0)
There's nothing wrong with long explanations that accurately depict complex issues. :-) The power companies are counting on no one being able to give one, and no one else being able to understand one.

So, the big picture is: the power companies are trying to use the threat of a deadline and the threat of federal intervention as reasons for state regulatory "rubber-stamping" of their applications.

Meanwhile, for states in the 4th circuit any single state involved actually does have the power to kill the entire project (or, for states in the middle, require it to be rerouted around that state, effectively killing it).

Depending on what happens in the Fall climate change bill, (a) state's rights may be expanded to all states East of the Mississippi, (b) the status quo may remain (e.g., just the 4th circuit states retain the right), or (c) FERC may get more power to intervene everywhere.

Of course, other circuits and/or the supreme court could always weight in on the issue, too, but that's not on the immediate horizon.

Is that about right?


[ Parent ]
Good summary. (4.00 / 1)
It is still unknown whether FERC will appeal the 4th Circuit decision any higher.  That is the only change in the situation you describe.

Comments by AEP CEO in his conference call last Friday indicate that AEP's lobbyists are working hard in the Senate to get Cheney's NIETC rules put in place for the eastern US.


[ Parent ]
Strategy - not strategery! (4.00 / 1)
And all of this illustrates why it's important to both fight PATH - our personal "ground battle" - and think strategically about the big picture of national energy policy. If the PSC rules against us on PATH and gives the go-ahead, that might not be the final word if it's contrary to a new federal energy policy (please note the conditional term "might").

Thanks for a great answer, Calhouner, and insightful questions, Clem!


[ Parent ]
Premium Advertiser

blog advertising is good for you

Welcome!

( Home )
Menu

Click here to join!

Username:

Password:



Forget your username or password?


About
- About WVaBlue.com
- Send us news at wvablue@gmail.com
-  Subscribe in a reader

Advertisers


Support WVaBlue

Active Users
Currently 0 user(s) logged on.

Search




Advanced Search


Current CO2 level in the atmosphere

Proudly displaying the West Virginia Red, White, Blue, Green and Orange.

Join me at http://www.350.org


WVa Democrats
  • Sen. Jay Rockefeller
  • Sen. Joe Manchin III
  • Joe Manchin for Senate (2010/2012)
  • Rep. Nick Rahall (WV-03)
  • Secretary of State Natalie Tennant
  • Auditor Glen Gainer
  • Treasurer John Perdue
  • Agriculture Commissioner Gus Douglass
  • Attorney General Darrell V. McGraw
  • Senate President Earl Ray Tomblin, acting as Gov.
  • Declared Candidates
  • Jeff Kessler
  • John Perdue
  • Natalie Tennant
  • Earl Ray Tomblin
  • Rick Thompson

  • Copyright 2011 West Virginia Blue
    Site content may be used for any purpose without explicit permission unless otherwise specified.
    This site exists thanks to financial support from BlogPAC, dedicated volunteers and participation by members of this community. The views expressed at West Virginia Blue belong solely to their respective authors.
    Powered by: SoapBlox